Conversion of a production plant

Röring converted a feeder panel and upgraded the existing switchgear for a lime production plant. Since the power station was a permanent installation, the work was carried out on-site at Rheinkalk's premises with the company's own copper machining centre. The modernisation was completed very quickly so that the production plant's specified downtime of maximum four hours could be respected.

 

referenz-13-1referenz-13-2referenz-13-3-thumbreferenz-13-4referenz-13-5referenz-13-6

< Back to reference overview